Saint Paul logo
File #: RLH RR 18-49    Version:
Type: Resolution LH Substantial Abatement Order Status: Passed
In control: City Council
Final action: 1/9/2019
Title: Making finding on the appealed nuisance abatement ordered for 544 MINNEHAHA AVENUE WEST in Council File RLH RR 17-12.
Sponsors: Dai Thao
Ward: Substantial Abatement Orders, Ward - 1
Attachments: 1. 544 Minnehaha Ave West.30 Day Forfeit Notice.10-8-18.pdf, 2. 544 Minnehaha Ave W.Making Finding Ltr.11-2-18.pdf, 3. 544 Minnehaha Ave W.Photos.11-13-18.pdf, 4. 544 Minnehaha Ave W.CC Findings RR Ltr.11-15-18.pdf, 5. 544 Minnehaha Ave W.Email and Work Timelines.11-27-18.pdf, 6. 544 Minnehaha Ave W.Landbank Remaining Impact Funds.pdf, 7. 544 Minnehaha Ave W.Seeger Comments.1-2-19
Related files: RLH RR 17-12, RLH RR 17-48
Title
Making finding on the appealed nuisance abatement ordered for 544 MINNEHAHA AVENUE WEST in Council File RLH RR 17-12.

Legislative Hearing Staff Comments
Legislative Hearing continued from 12/26/17 to 1/16/18. Council hearing 1/17/18. Council Public Hearing scheduled for January 17, 2018.

Body
AMENDED 1/9/19

WHEREAS, the City Council adopted RLH RR 17-12 on June 21, 2017 which granted 180 days to abate the nuisance conditions at 544 Minnehaha Avenue West; and

WHEREAS, the Legislative Hearing Officer reviewed this case on December 26, 2017, January 16, 2018, January 30, 2018 and February 13, 2018 to determine if the owner and/or responsible party abated the nuisance conditions and found these conditions were not abated;

WHEREAS, the Legislative Hearing Officer, based on results from these hearings which indicate the project is 30% complete 7.5 months after the 6-month grant of time from the City Council on June 28, 2017, recommends that, in order to receive an 180-day extension: 1) revised work plans with current contractors, budgets and documentation of financial capacity be submitted and approved; 2) the initial $5,000 performance deposit be continued and 3) a second $5,000 performance deposit be posted by February 23, 2018; and

WHEREAS, these conditions were not met by the above-established deadline; however, Council gave 3 additional extensions for the conditions to be met and they were met by Council meeting time on March 21, 2018; and

WHEREAS, the above listed were met, albeit well-past the original deadline, the Legislative Hearing Officer recommends that the City Council grant to September 14, 2018 for the nuisance building to be abated by razing and removal or rehabilitation, as evidenced by issuance of a Certificate of Code Compliance; and

WHEREAS, the Saint Paul City Council adopts the finding of the legislative hearing officer that the nuisance condition is not abated; however, conditions for an additional grant of time for the abat...