Saint Paul logo
File #: RES PH 21-115    Version:
Type: Resolution-Public Hearing Status: Passed
In control: City Council
Final action: 5/12/2021
Title: Establishing Wabasha Street as the west corridor of the Capital City Bikeway downtown bike network.
Sponsors: Rebecca Noecker
Attachments: 1. Wabasha Street_SOER_Final_050521_reduced, 2. CCB Wabasha Street Rec Feedback April 2021, 3. Markham Corporation Coalition Letter for Capitol City Bikeway 2021.05.05, 4. TC recommendation- CCB Interim Design Wabasha, 5. RES PH 21-115 - Randy Newton-Public Works, 6. Hannah Laurents_Ward 3, 7. RES PH 21-115 - Elizabeth Aulwes, 8. RES PH 21-115 - Elizabeth Aulwes #2, 9. RES PH 21-115 - Adam DeLong, 10. RES PH 21-115 - Timothy J. Dwyer-The Markham Company, 11. RES PH 21-115 - Cristopher Berlin-Gibson, 12. RES PH 21-115 - Beth Butala, 13. RES PH 21-115 - Chari Hall-History Theatre, 14. RES PH 21-115 - Moges Keleta, 15. RES PH 21-115 - Christy Klancher, 16. RES PH 21-115 - Allison Klis-The Terrace Group, 17. RES PH 21-115 - Nathan Kranz, 18. RES PH 21-115 - Brenda Lamb-Candyland, 19. RES PH 21-115 - Doug Lamb-Candyland, 20. RES PH 21-115 - Hannah Lehman, 21. RES Ph 21-115 -Sarah Lippert, 22. RES PH 21-115 - Bob Long, 23. RES PH 21-115 - The Loon Cafe, 24. RES PH 21-115 - Debbie Mishler, 25. RES PH 21-115 - Debbie Mishler #2, 26. RES PH 21-115 - Hampton & Sher O'Neill, 27. RES Ph 21-115 - Brenda Peters-Amsterdam Bar & Hall, 28. RES PH 21-115 - Mary Reis, 29. RES PH 21-115 - Rice Park Association letter, 30. RES PH 21-115 - Renee Schaefer, 31. RES PH 21-115 - Nancy Schumacher-Church of Scientology of Twin Cities, 32. RES PH 21-115 - Jay Severance, 33. RES PH 21-115 - Andy Singer-St Paul Bicycle Coalition, 34. RES PH 21-115 - St. Peter Street Properties, 35. RES PH 21-115 - Gina Smith, 36. RES PH 21-115 - Kathleen Weiker-Victory Parking, 37. Ward 2 Public Comments on Bikeway, 38. Feedback on Bikeway Plan
Title
Establishing Wabasha Street as the west corridor of the Capital City Bikeway downtown bike network.

Body
WHEREAS, the Council of the City of Saint Paul approved the Capital City Bikeway Network Study and Design Guide and adopted it into the Saint Paul Bicycle Plan on July 19, 2017 (RES 17-150); and

WHEREAS, the City of Saint Paul Department of Public Works was directed to re-evaluate and determine the preferred route and conceptual design of the west corridor of the Capital City Bikeway downtown bike network as part of the Capital City Bikeway Interim Design Study; and

WHEREAS, improving the network of safe bikeways across the City of Saint Paul is consistent with the Transportation Chapter of the City’s Comprehensive Plan and the City’s Climate Action and Resilience Plan; and

WHEREAS, improving access for safe bicycling in downtown Saint Paul will make it easier and safer for people to choose to bicycle for transportation and recreation, which helps to promote a healthier community; and

WHEREAS, Public Works is planning a reconstruction of Wabasha Street between Kellogg Boulevard and 6th Street in 2022; and

WHEREAS, Public Works is planning a mill and overlay of Wabasha Street between 6th Street and 11th Street in 2022; and

WHEREAS, Public Works has gathered input, presented information, and received feedback on the Capital City Bikeway Interim Design Study project through three community meetings, a virtual presentation, online surveys, and small group meetings; and

WHEREAS, multiple interim and full build design concepts were developed for the west corridor of the Capital City Bikeway and presented to the community, and revised in response to community feedback; and

WHEREAS, the Wabasha Street corridor Summary of Engineering Recommendations dated May 5, 2021 provides documentation of the Capital City Bikeway Interim Design Study project process and recommendation; and

WHEREAS, Public Works has identified the west side of Wabasha Street b...

Click here for full text
Date NameDistrictOpinionCommentAction
No records to display.