Title: Amending the financing and spending plan in the Department of Parks and Recreation in the amount of $77,800 to reflect funds received from the Lower Phalen Creek Project for staff design services for the Wakan Tipi project.
Sponsors: Jane L. Prince
Ward: Grant, Lower Phalen Creek Project, Wakan Tipi
Attachments: 1. Wakan Tipi LPCP FS Sheet Dec'20

Title

Amending the financing and spending plan in the Department of Parks and Recreation in the amount of $77,800 to reflect funds received from the Lower Phalen Creek Project for staff design services for the Wakan Tipi project.

 

Body

WHEREAS, the City of Saint Paul, through its Department of Parks and Recreation, is providing technical design support for predesign of the proposed Wakan Tipi Center at Bruce Vento Nature Sanctuary; and

 

WHEREAS, the Lower Phalen Creek Project (LPCP) received $3 million in State bonds and is actively pursuing private donations and grants; and

 

WHEREAS, the City and the LPCP has entered into a development agreement with LPCP operating and maintaining Wakan Tipi Center under a long-term lease; and

 

WHEREAS, LPCP has agreed to provide $77,800 to the Department for project management and design work; and

 

WHEREAS, it is the desire of Parks and Recreation to amend the financing and spending budget for the project in the amount of $77,800; and

 

WHEREAS, the Mayor, pursuant to Section 10.07.1 of the Charter of the City of Saint Paul, does certify that there are available for appropriation, funds of $77,800 in excess of those estimated in the 2021 Capital Improvement Budget; now, therefore, be it

 

RESOLVED, by the City Council of the City of Saint Paul, upon recommendation of the Mayor and the advice of the Long Range Capital Improvement Budget Committee, that $77,800 is available for appropriation in the 2021 Capital Improvement Budget, and said 2021 budget, as therefore adopted by the Council, is hereby further amended.

 

 

Financial Analysis

 

See Attachment

 

CIB Recommendation

The St. Paul Long-Range Capital Improvement Budget Committee received this request on December 14, 2020 and recommended approval.

 

Date NameDistrictOpinionCommentAction