Title
Appeal of Heather Cothern to a Fire Inspection Correction Notice - Certificate of Occupancy at 213 BATES AVENUE.
Date/Time of 1st LH: August 28, 2018 at 1:30
Purpose of Appeal: We are only appealing the time frame. This is a historical building and we need more time to complete the work as we have to get approval from them on all outside work.
Date of Order(s) Under Appeal: August 17, 2018
Inspector/Key Staff: Brian Schmidt
Legislative Hearing Staff Comments:
Body
WHEREAS, in the matter of Appeal of Heather Cothern to a Fire Inspection Correction Notice - Certificate of Occupancy at 213 BATES AVENUE, the Legislative Hearing Officer has reviewed the appeal and considered the testimony of City staff and the appellant; and
WHEREAS, the Legislative Hearing Officer recommends that the City Council grant an extension to December 1, 2018 to bring exterior building items (Items 1-4) into compliance and to October 1, 2018 for the balance of the orders; Now, Therefore, Be It
RESOLVED, that the Saint Paul City Council hereby accepts and adopts the Legislative Hearing Officer's recommendation in this matter.