File #: RES PH 18-263    Version: 1
Type: Resolution-Public Hearing Status: Passed
In control: City Council
Final action: 9/5/2018
Title: Approving the application of Insituform for a sound level variance to allow for a cure-in-place sewer liner project on Orange Avenue West between Virginia Street and Farrington Street for a single overnight process between October 1 and December 31, 2018.
Sponsors: Amy Brendmoen
Ward: Ward - 5
Attachments: 1. Application, 2. ENS, 3. Map, 4. Notice to Owners, 5. List of Owners, 6. Letter to Applicant

Title

Approving the application of Insituform for a sound level variance to allow for a cure-in-place sewer liner project on Orange Avenue West between Virginia Street and Farrington Street for a single overnight process between October 1 and December 31, 2018.

 

Body

WHEREAS, Chapter 293 of the Saint Paul Legislative Code was enacted to regulate the subject of noise in the City of Saint Paul; and

 

WHEREAS, §293.09 provides for the granting of variances from the sound level limitations contained in §293.07, upon a finding by the City Council that full compliance with Chapter 293 would constitute an unreasonable hardship on the applicant, other persons or on the community; and

 

WHEREAS, Insituform, represented by Patrick Hillan, has applied for a sound level variance for sewer construction work, with use of heavy trucks with internal generators and hydraulic pumps during a sewer lining project for a single 24 hour process between October 1 and December 31, 2018. The project proposes to allow elevated sound levels during one 24 hour per day period on Orange Avenue West between Virginia Street and Farrington Street, with a sewer liner curing process requiring 24 hours of continuous work. Applicant indicates the site set up to occur from 7:00 a.m. to 5:00 p.m., with use of equipment with back up alarms and hand held power tools. From 5:00 p.m. until 7:00 a.m. of the following day, the only equipment to be used will be critically silenced pumps and truck mounted boiler, not to exceed 70 decibels (dBA) at 50 feet; and

 

WHEREAS, in order to meet required City of Saint Paul project completion and to minimize disruption to traffic, area businesses, the public, adjoining residents and property owners, the applicant is seeking a variance during the period of October 1 and December 31, 2018. The applicant is requesting one twenty-four hour per day operation at the site for continuous cured in place sewer lining work; and

 

WHEREAS, if applicant is not granted the variance, Insituform will not be able to operate general construction/demolition equipment and other repair and installation equipment and power tools needed to complete the rehabilitation of deteriorated and corroded damage to the sewer pipes project on Orange Avenue West between Virginia Street and Farrington Street; and

 

WHEREAS, the Department of Safety and Inspections has reviewed the application and has made recommendations regarding conditions for the variance.  Now, therefore, be it

 

RESOLVED, that the Council of the City of Saint Paul hereby grants a sound level variance to Insituform, subject to the following conditions:

 

1) The variance will be for operating general construction/demolition equipment and other repair and installation equipment for replacement, set up and installation of a cured in place sewer pipe. Rehabilitation of the deteriorated and corroded damage to sewer pipes is required. Work is to take place on Orange Avenue West between the Virginia Street and Farrington Street site; beginning  October 1 through December 31, 2018.

 

2)   The variance will include one, twenty-four hour per day operation at the site, 7:00 a.m. to 7:00 a.m., with site set up from 7:00 a.m. until 5:00 p.m. for use of equipment with back up alarms and hand held power tools. From 7:00 p.m. until 7:00 a.m. of the following day, critically silenced pumps and truck mounted boiler equipment, both under 70 decibels (dBA) at fifty (50) feet will be used during the continuous work period at the construction site.

 

3)  The applicant shall provide personnel and equipment to ensure compliance with the variance conditions.

 

4)  If the variance is approved, Insituform will notify in writing, all property owners/residents within 400 feet of the proposed work location. Notification shall be a minimum of forty-eight (48) hours prior to the start of the work.

 

If there is a need for additional overnight elevated noise shifts, Insituform must submit an Extended Work Request (EWR) to the Department of Safety and Inspections (DSI). 

 

A.                      Insituform must submit an EWR, in writing, to DSI a minimum of four (4) work days before the start date of additional overnight elevated noise shift.

B.                     The request will include, but not be limited to, the specific date, time period, location, operation description and listing of expected noise sources.

C.                     The EWR shall also include the name and phone number of a specific contact person for the work being done.

D.                     Within two (2) working days of receiving the request, DSI, in consultation with the appropriate councilmember, shall review and approve or deny the specific request and forward the determination to Insituform.

E.                     If the request is approved, Insituform will notify in writing, all property owners/residents within 400 feet of the proposed work location. Notification shall be a minimum of forty-eight hours prior to the start of the work.

F.                     When an EWR is approved, DSI will provide Insituform with a list of property owners/residents within 400 feet of the work location that are to be notified.

FURTHER RESOLVED, that any violations of the conditions set forth above on any of the dates may result in revocation of the grant of a variance for the subsequent date(s), in addition to any criminal citation which might issue.

 

Required Background Information

Insituform has requested an exemption from the sound level limitations in Chapter 293.07 for operating general construction/demolition equipment and other repair and installation equipment for replacement, set up and installation of a cured in place sewer pipe at the location. Rehabilitation of the deteriorated and corroded damage to the sewer pipes is required. The location is Orange Avenue West between Virginia Street and Farrington Street. A 24-hour cure in place work process is to occur between October 1 and December 31, 2018.  Chapter 293.09 provides for the granting of variances from the sound level limitations contained in Chapter 293.07.

 

Was proper notice given?  YES - See Attachments

 