Title: Approving the application of Veit and Company Inc. for a sound level variance in order to allow pile driving of beams for retaining wall shoring during building excavation at Fifth Street East and Broadway Street, for up to three (3) days from 7:00 a.m. to 5:00 p.m. between December 9, 2013 and December 20, 2013.
Sponsors: Dave Thune
Ward: Ward - 2
Attachments: 1. Veit SLV Application.pdf, 2. Veit ENS.pdf, 3. Veit Applicant Ltr.pdf, 4. Veit DC17 Notification.pdf, 5. Veit Map 2013.pdf, 6. Veit Property Owner List.pdf, 7. Veit Example Letter.pdf, 8. Russo opposition to Veit sound variance
Title
Approving the application of Veit and Company Inc. for a sound level variance in order to allow pile driving of beams for retaining wall shoring during building excavation at Fifth Street East and Broadway Street, for up to three (3) days from 7:00 a.m. to 5:00 p.m. between December 9, 2013 and December 20, 2013.

Body
WHEREAS, Chapter 293 of the Saint Paul Legislative Code was enacted to regulate the subject of noise in the City of Saint Paul; and

WHEREAS, §293.09 provides for the granting of variances from the sound level limitations contained in §293.07, upon a finding by the City Council that full compliance with Chapter 293 would constitute an unreasonable hardship on the applicant, other persons or on the community; and

WHEREAS, Nate Iverson, Project Manager, Veit and Company Inc. who has been designated as the responsible person on the application, has applied for a variance to allow Pile Driving for retaining wall shoring at 5th Street East and Broadway Street; and

WHEREAS, in order to minimize disruption to adjoining property owners, residents and businesses, the applicant is seeking a variance for the hours of 7:00 AM to 5:00 PM and for up to three (3) days, between December 9, 2013 and December 20, 2013; and

WHEREAS, if applicant is not granted a variance it will not be able to complete construction within a timeline that would minimize disruption to businesses, the public and adjoining property owners; and

WHEREAS, the Department of Safety and Inspections has reviewed the application and has made recommendations regarding conditions for the variance; now, therefore, be it

RESOLVED, that the Council of the City of Saint Paul hereby grants a variance to Veit and Company Inc., subject to the following conditions:

1) The variance shall be for pile driving activities occurring on not more than three (3) days between December 9, 2013 and December 20, 2013 and the hours of 8:00 AM to 5:00 PM.

2) Veit and Company will provide...