Saint Paul logo
File #: RES PH 18-361    Version: 1
Type: Resolution-Public Hearing Status: Passed
In control: City Council
Final action: 12/5/2018
Title: Approving a Preliminary Design Study for the Canadian Pacific Ford Spur.
Sponsors: Rebecca Noecker, Chris Tolbert
Attachments: 1. Ford Spur Final Report_11_19_18, 2. Ford Spur Final Report - Appendix, 3. Ford Spur Study PC Resolution, 4. PC Action Minutes, 5. PC Approved Minutes, 6. Bengel Email, 7. PED Staff Spur Presentation, 8. Fort Road Fed Resolution Ford Spur 4.11.2018 PASSED
Title

Approving a Preliminary Design Study for the Canadian Pacific Ford Spur.

Body

WHEREAS, the Canadian Pacific (CP) Ford Rail Spur is no longer used to serve the Ford Motor Company Twin Cities Assembly Plant; and

WHEREAS, the CP Ford Spur represents an opportunity to provide important transportation and recreation options by incorporating multiple modes of transportation in a corridor that passes through diverse neighborhoods; and

WHEREAS, the Saint Paul City Council passed Resolution 14-723 in April 2014 authorizing the Department of Planning and Economic Development to apply for a Federal TIGER VI Planning Grant to prepare a plan for the Canadian Pacific Ford Rail Spur; and

WHEREAS, the United States Department of Transportation (“DOT”) awarded a $100,000 grant (FHWA FY 2014 TIGER Planning Grant No. P-18, T14HP039; S.P. # 164-070-014) to the City of Saint Paul to be used in the preparation of a preliminary design study (“Study”) of the Canadian Pacific Ford Rail Spur to identify constraints and opportunities for multi-modal use and develop preliminary design concepts; and

WHEREAS, the Grant was combined with $70,000 from the pre-development account of the Loan Enterprise Fund Budget of the Housing and Redevelopment Authority of the City of Saint Paul to fund the Study; and

WHEREAS, East Metro Strong generously donated $20,000 to the City of Saint Paul to be used in support of the Study; and

WHEREAS, Ford Motor Company generously donated $10,000 to the City of Saint Paul to be used in support of the Study; and

WHEREAS, a project team led by Alta Planning + Design and Planning Commission staff, and supported by Sambatek and Kimley-Horn, undertook a study of the CP Ford Spur using the grant application and agreement as guides; and

WHEREAS, Project and Technical Advisory Groups were assembled to represent stakeholder interests and provide input throughout the Study process; and

WHEREAS, a series of community forums was held between May ...

Click here for full text
Date NameDistrictOpinionCommentAction
No records to display.