WHEREAS, the City plans to construct sidewalks on McKnight from Mailand to Londin Lane and on Randolph from Toronto to Shepard; and
WHEREAS, the City plans to include the McKnight sidewalk with the 2020 Randolph Sidewalk Project; and
WHEREAS, Ramsey County has agreed to fund 50% of these projects; and
WHEREAS, the project estimates have identified a need for additional County and City funding; and
WHEREAS, there is a need to add $200,000 of Ramsey County funding to the 2020 Randolph Sidewalk Project; and
WHEREAS, there is a need to transfer $200,000 of MSA from 2021 MSA Contingency to the 2020 Randolph Sidewalk Project; and
WHEREAS, the Mayor, pursuant to Section 10.07.1 of the Charter of the City of Saint Paul, does certify that there is available for appropriation funds of $200,000; and
WHEREAS, the Mayor, pursuant to Section 10.07.4 of the Charter of the City of Saint Paul, does certify that there is available for transfer of appropriation funds of $200,000; now, therefore be it
RESOLVED by the Council of the City of Saint Paul, upon recommendation of the Mayor and advice of the Long Range Capital Improvement Budget Committee, that $200,000 is available for appropriation and that $200,000 is available for transfer of appropriation in the Capital Improvement Budgets, as heretofore adopted and amended by this Council, be hereby further amended in the Improvements Budgets in the following particulars:
Financial Analysis
See Attachment.
CIB Recommendation
The St. Paul Long-Range Capital Improvement Budget Committee received this request on March 8, 2021 and recommended approval.