Saint Paul logo
File #: RES 23-299    Version: 1
Type: Resolution Status: Passed
In control: City Council
Final action: 3/8/2023
Title: Preliminary Order setting the date of Public Hearing for April 12, 2023 to consider approval of the 2023 Saint Paul Streets Program (2023 SPS).
Sponsors: Rebecca Noecker
Attachments: 1. Summary of Engineering Recommendations, 2. Minnesota Street Assessment Roll, 3. Summary of Engineering Recommendations, 4. Annapolis Street Assessment Roll, 5. Special Assmts. Memo 2.16.2023 - 2023 SPS Projects

Title

Preliminary Order setting the date of Public Hearing for April 12, 2023 to consider approval of the 2023 Saint Paul Streets Program (2023 SPS).

Body

In the Matter of approving all necessary work for the reconstruction of streets in the 2023 Saint Paul Streets Program, proposed improvements are outlined for each project area in the attached Summary of Engineering Recommendations.

 

The streets to be improved are as follows:

 

Minnesota Street: Kellogg to 6th, Phase I

Annapolis Street: Smith to Robert, Phase I

 

The Council of the City of Saint Paul, having received the report of the Mayor upon the above improvement and having considered said report, hereby resolves:

 

1. That the said report and the same is hereby approved with no alternatives, and that the estimated cost thereof is $8,824,099, financed by Street Reconstruction Bonds, Municipal State Aid, Saint Paul Regional Water Services funding, and Sewer funds.

 

2. That a public hearing be had on said improvement on the 12th day of April, 2023, at 3:30 p.m., in the Council Chambers of the City Hall and Court House Building in the City of Saint Paul.

 

3. That notice of said public hearing be given to the persons and in the manner provided by the Charter, stating the time and place of hearing, the nature of the improvement and the total cost thereof as estimated.

 