Title: Preliminary Order setting the date of Public Hearing for June 26, 2024 to consider approval of the 2024 Mill and Overlay Program.
Sponsors: Mitra Jalali
Attachments: 1. Special Assmts. Memo - 2024 MO Projects FINAL - 4.2.24, 2. Residential Mill Overlay - Summary of Engineering Recommendations, 3. Cretin/Bayard Area (Residential) - Assessment Roll, 4. Fourth/Howard Area (Residential) - Assessment Roll, 5. Arterial Mill Overlay - Summary of Engineering Recommendations, 6. Front-Western to Rice (Arterial) - Assessment Roll, 7. Concordia-Snelling to Marion (Arterial) - Assessment Roll

Title

Preliminary Order setting the date of Public Hearing for June 26, 2024 to consider approval of the 2024 Mill and Overlay Program.

Body

In the Matter of approving all necessary work for the mill and overlay of streets in the 2024 Mill and Overlay Program, proposed improvements include removal of the top layer (2”) of the street and placing a new layer of bituminous pavement.

 

The streets to be improved are as follows (see maps):

 

Arterial

Concordia/St. Anthony from Snelling Ave. to Marion St.

Front Ave. from Western Ave. to Rice St.

 

Residential

Cretin-Bayard Area (Phase II)

Fourth-Howard Area (Phase I)

 

The Council of the City of Saint Paul, having received the report of the Mayor upon the above improvement and having considered said report, hereby resolves:

 

1. That the said report and the same is hereby approved with no alternatives, and that the estimated cost thereof is $9,595,394, financed by street reconstruction bonds, general fund, sidewalks, MnDot, and assessments.

 

2. That a public hearing be had on said improvement on the 26th day of June, 2024, at 3:30 p.m., in the Council Chambers of the City Hall and Court House Building in the City of Saint Paul.

 

3. That notice of said public hearing be given to the persons and in the manner provided by the Charter, stating the time and place of hearing, the nature of the improvement and the total cost thereof as estimated.

 

 