WHEREAS, The Highland Parkway area demonstrated signs of pavement degradation that require a mill and overlay to extend its service life and to minimize the costs of ongoing pothole repairs; and
WHEREAS, the Highland Parkway Mill and Overlay project was completed in 2017 as part of the Public Works mill and overlay program; and
WHEREAS, there is a 2015 approved capital project, the Arterial/Collector Street Overlay Program, to assist with the Right of Way overlay program with a goal to address deteriorating streets throughout the City and supplement other Right of Way program funding; and
WHEREAS, the cost of the Highland Parkway Mill and Overlay project is $262,479.61; and
WHEREAS, the total $250,000 capital budget is available to be transferred to the Right of Way fund; and
WHEREAS, the Department of the Public Works Director and City Engineer have requested to transfer $250,000 of capital financing, which will increase the spending and financing budget in the Right of Way fund; and
WHEREAS, the Mayor, pursuant to Section 10.07.1 of the Charter of the City of Saint Paul, does certify that there are available for appropriation, funds of $250,000 to be transferred;
NOW, THEREFORE, BE IT RESOLVED that Council of the City of Saint Paul, upon recommendation of the Mayor, approves the amendments to the operating and capital budgets as detailed in the attached financial analysis.