File #: RES 19-120    Version: 2
Type: Resolution Status: Passed
In control: City Council
Final action: 2/6/2019
Title: Authorizing not using a Project Labor Agreement (PLA) for the following projects: Sewer Cleaning and Televising Projects (Cleveland-Youngman, Montreal-Woodlawn, Snelling-Juno), MRB Sanitary Tunnel Cleaning, Tunnel Shafts, Flandrau-Case Stormwater Facility Improvements, 2019 Citywide Sewer Lining, and 2019 Citywide Sewer Repairs.
Sponsors: Amy Brendmoen
Attachments: 1. RES 19-120 Financial Analysis
Title
Authorizing not using a Project Labor Agreement (PLA) for the following projects: Sewer Cleaning and Televising Projects (Cleveland-Youngman, Montreal-Woodlawn, Snelling-Juno), MRB Sanitary Tunnel Cleaning, Tunnel Shafts, Flandrau-Case Stormwater Facility Improvements, 2019 Citywide Sewer Lining, and 2019 Citywide Sewer Repairs.

Body
WHEREAS, the Saint Paul City Council has adopted a policy on the use of Project Labor Agreements ("PLA") pursuant to Council File #09-584 for projects involving $250,000 or more of city money; and

WHEREAS, the Public Works Sewer Utility is undertaking sewer related cleaning, inspection, and repair projects, with project total budgets over $250,000;

Sewer Cleaning and Televising Projects
(3- projects; Cleveland-Youngman, Montreal-Woodlawn, Snelling-Juno)
Project Description: Clean and televise sanitary sewers and manholes, and televise storm sewers and manholes
Estimated Cost: $500,000 for each project
Estimated Start Date: Spring 2019
Estimated Project Timeline: 6 months

MRB Sanitary Tunnel Cleaning Project
Project Description: Clean deep sanitary tunnel within corridor of Mississippi River Boulevard
Estimated Cost: $700,000
Estimated Start Date: Fall of 2019
Estimated Project Timeline: 3-4 months

Tunnel Shafts Project
Project Description: Construct two to four new tunnel shafts to enable tunnel maintenance and repairs
Estimated Cost: $2,400,000
Estimated Start Date: Fall of 2019 or 2020
Estimated Project Timeline: 6 months

Flandrau-Case Stormwater Facility Improvements Project.
Project Description: Modify existing facility to improve stormwater quality and detention benefits, and access for maintenance
Estimated Cost: $1,000,000
Estimated Start Date: 2019 or 2020
Estimated Project Timeline: 6 months

2019 Citywide Sewer Repair Project
Project Description: Repair broken sewer piping and/or manholes via excavation in public streets
Estimated Cost: $500,000
Estimated Start Date: Spring 2019
Estimated Projec...