Title
Final Order approving 2026 Wheelock/Grotto Phase II Area Paving and Lighting; and Mill and Overlay Project (Project 19277 and MO2604, Asmt 265200 and 265203).
Body
In the Matter of approving all necessary work for the 2026 Wheelock/Grotto, phase II paving and lighting and mill and overlay project, proposed improvements to be made as part of the project include constructing new bituminous surfaced streets with concrete curb and gutter, concrete driveway aprons and boulevards landscaped with sod and trees. Damaged sidewalks will be replaced as necessary. Sidewalks will be added where appropriate. The existing wood pole streetlights will be replaced with lantern style lights as part of the project. In addition, new watermain will be installed, appropriate storm and sanitary sewer repairs will be made, and storm and sanitary sewer reconnections will be made at the request of property owners.
Grotto St. between Lakeview and Arlington Avenue, and Orange St. between Grotto and Dale, will be milled and overlaid.
Under Preliminary Order: RES 25-1842 Approved 12/10/2025
WHEREAS, the Council of the City of Saint Paul has conducted a public hearing upon the above improvement, due notice thereof having been given as prescribed by the City Charter; and
WHEREAS, the Council has heard all persons, objections and recommendations pertaining to said proposed improvement and has fully considered the same; now, therefore, be it
RESOLVED, that the Council of the City of Saint Paul does hereby order that the above-described improvement be made, and the proper City officers are hereby directed and authorized to proceed with the improvement; and be it
FINALLY RESOLVED, that upon the completion of said improvement, the proper City officers shall calculate all expenses incurred therein and shall report the same to the City Council in accordance with Chapter 14 of the City Charter.