Saint Paul logo
File #: RLH RR 24-8    Version:
Type: Resolution LH Substantial Abatement Order Status: Passed
In control: City Council
Final action: 3/27/2024
Title: Second Making finding on the appealed substantial abatement ordered for 733 FAIRVIEW AVENUE NORTH in Council File RLH RR 23-11.
Sponsors: Mitra Jalali
Ward: Substantial Abatement Orders, Ward - 4
Attachments: 1. 733 Fairview Ave N.30 Day Forfeit Ltr 1-9-24.pdf, 2. 733 Fairview Ave N.Skliris Notice of PH 1-26-24.pdf, 3. 733 Fairview Ave N.Zane emai.2-14-23, 4. 733 Fairview Ave N.Skliris R-R Ltr.2-16-24, 5. 733 Fairview Ave N.Skliris R-R Ltr.3-1-24, 6. 733 Fairview Ave. N. Ubl Email.3-11-24, 7. 733 Fairview Ave N.Skliris Zimny email.3-12-24, 8. 733 Fairview Ave N.Skliris R-R Ltr.3-15-24
Related files: RLH VBR 16-56, RLH RR 22-28, CO 22-11, RLH RR 23-11, RLH RR 24-43, RLH RR 24-26
Title
Second Making finding on the appealed substantial abatement ordered for 733 FAIRVIEW AVENUE NORTH in Council File RLH RR 23-11.

Body
WHEREAS, the City Council adopted RLH RR 23-11 on August 9, 2023 which granted an extension of 180 days to repair the structure, correct all of the deficiencies listed in the Code Compliance Report at 733 Fairview Avenue North; and

WHEREAS, the Legislative Hearing Officer reviewed this case on February 13, February 27 and March 12, 2024, to determine if the owner and/or responsible party abated the nuisance conditions;

WHEREAS, the Legislative Hearing Officer found these conditions were not abated; but recommends that the CIty Council 1) grant an additional 90 days to rehabilitate; and 2) continue the $5,000 Performance Deposit:

WHEREAS, per the February 27, 2024 meeting between the owner and the Building Official, an understanding and agreement was reached whereby a Certificate of Code Compliance would be granted upon the following items being addressed:

1.The range hood vent is a 600 CFM exhaust appliance. It must be installed per manufacture’s recommendations with make-up air or be removed with an appliance that is 300 CFM or smaller.
2.The ductwork will need to be inspected with the requirement that the interior is sprayed the interior with an approved sealant; or a contractor must scope the ductwork for inspection.
3.There is a new deck installed which was not part of the scope of work under the building permit (scope of work under the building permit was for the team, code compliance list). Therefore, the decking will need to be removed to inspect the structure.
4.The owner agrees to have the plumbing contractor contact the plumbing inspector and schedule an on-site inspection to generate a list of requirements/deficiencies/items needing to be completed under a plumbing permit. Note, the plumbing inspector contacted the plumbing contractor, Mr. Maison Plumbing and Drain LLC, who applied for a plumbing permit for a...

Click here for full text
Date NameDistrictOpinionCommentAction
No records to display.