Skip to main content
Saint Paul logo
File #: RES 25-1625    Version: 1
Type: Resolution Status: Mayor's Office
In control: City Council
Final action: 10/22/2025
Title: Approving Ordinance Permit 20240020401 for Storm Sewer Infrastructure installed by the Saint Paul Port Authority on The Heights project site (at the following locations: on Winthrop Street from Ivy Avenue (MH5006) to Clear Street (MH5008), Cottage Avenue (MH5018) to Sherwood Avenue (MH5080), and at Arlington Avenue (MH5058 to MH5057); on Howard Street from Ivy Avenue (MH5109) to Arlington Avenue (MH5053); on Arlington Avenue from Howard Street (MH5053) to Winthrop Street (MH5057)).
Sponsors: Nelsie Yang
Attachments: 1. 20240020401 - Exhibit A-ForCouncil.pdf

Title

Approving Ordinance Permit 20240020401 for Storm Sewer Infrastructure installed by the Saint Paul Port Authority on The Heights project site (at the following locations: on Winthrop Street from Ivy Avenue (MH5006) to Clear Street (MH5008), Cottage Avenue (MH5018) to Sherwood Avenue (MH5080), and at Arlington Avenue (MH5058 to MH5057); on Howard Street from Ivy Avenue (MH5109) to Arlington Avenue (MH5053); on Arlington Avenue from Howard Street (MH5053) to Winthrop Street (MH5057)).

Body

WHEREAS, the Saint Paul City Council has adopted the Hillcrest Master Plan and all Amendments to the Plan; and

 

WHEREAS, in 2019 Ordinance 19-39 was adopted by the City Council that provides for the SPPA as “…responsible for the design, engineering, construction and delivery of public infrastructure…” on The Heights project; and 

 

WHEREAS, in October of 2022 the SPPA submitted appropriate plans, reports, and exhibits to begin the Site Plan Review process for The Heights project under SPR# 23-064690; and

 

WHEREAS, Public Works’ Policy “Construction of Public Infrastructure by Private Developers Policy” provides minimum requirements for “…plan review of private developments seeking to install public infrastructure…” in the Public Right-of-Way; and

 

WHEREAS, the City’s Ordinance Permit Policy and associated Ordinances 122 & 123 provides for City installation of improvements completed by the SPPA on The Heights project; and

 

WHEREAS, the appropriate City Departments and City subject matter experts reviewed said Plans, Specifications, Reports, and Documents and found same to be in compliance with applicable Codes, Standards, and Policies such that approval with conditions was granted by the Department of Safety and Inspections on May 17, 2024 for the storm sewer system for site plan 23-064690; and

 

WHEREAS, on July 18, 2024 the appropriate Ordinance Permit was issued by the City to the SPPA for the purpose of completing certain storm sewer infrastructure improvements for The Heights project; and

 

WHEREAS, with the exception of possible warranty rework resulting from a future inspection(s) prior to the expiration of the warranty period and testing of sections (structure 5010 to 5109, structure 5010D to 5010, structure 5058A to 5058, structure 5058B to 5058) that are currently unavailable due to inundation of water or other reasons, the SPPA has completed the installation of certain public improvements for Ordinance Permit 20240020401 according to the requirements stated in Codes, Standards, and Specifications; and

 

WHEREAS, warranties are assigned per Codes, Standards, and Specifications; and

 

WHEREAS, the SPPA has satisfied the applicable requirements of the Ordinance Permit Acceptance process as required by Codes, Standards, and Policies for the installation of certain public improvements such that a recommendation is made to the City Council that the public infrastructure identified in Ordinance Permit 20240020401 be accepted; now, therefore be it

 

RESOLVED, that the City Council accepts the infrastructure as so defined in the attached Exhibit A and pursuant to Codes, Standards, and Specifications for commencement of the warranty period following Council acceptance.

 

 

Date NameDistrictOpinionCommentAction
No records to display.