Saint Paul logo
File #: RES PH 20-100    Version:
Type: Resolution-Public Hearing Status: Passed
In control: City Council
Final action: 4/22/2020
Title: Approving the 2020 Ayd Mill Road Multi-Modal Improvements Project and amending the financing and spending plans in the Department of Public Works Capital Budget to establish the project budget.
Sponsors: Amy Brendmoen
Code sections: Sec. 10.07.1. - Supplemental appropriations., Sec. 10.07.4. - Transfer of appropriations., Sec. 10.09. - Lapse of appropriations_Capital improvements.
Attachments: 1. March 19, 2020 Ayd Mill Road Presentation, 2. April 6, 2020 Ayd Mill Road Presentation, 3. Ayd Mill Road Survey Data - 4.1.2020, 4. April 6 Ayd Mill Rd Presentation Comments & Questions - 4.21.2020, 5. Ayd Mill Road General Comments or Questions 4.21.2020, 6. Comments on Ayd Mill Road - MM, 7. Ayd Mill Road- SHA April 2020, 8. Ayd Mill phone messages, 9. Ayd Mill email comment, 10. Action Network email and signatures, 11. Financial Analysis For Amendment (not adopted), 12. Noecker Amendment (not adopted)

Title

Approving the 2020 Ayd Mill Road Multi-Modal Improvements Project and amending the financing and spending plans in the Department of Public Works Capital Budget to establish the project budget.

 

Body

WHEREAS, the City of Saint Paul plans to construct the 2020 Ayd Mill Road Multi-Modal Improvements Project; and

 

WHEREAS, as per Council Resolution Public Hearing 20-50, the Department of Public Works conducted traffic modeling and analysis and held a public engagement process for the Ayd Mill Road Project; and

 

WHEREAS, Council Resolution Public Hearing 20-50 authorized the issuance of an additional $2,230,000 of Street Reconstruction Bonds for the 2020 Saint Paul Streets Program from the adopted budget; and

 

WHEREAS, there is a need to add this additional $2,230,000 of Street Reconstruction Bonds to the Ayd Mill Road Project; and

 

WHEREAS, there is a need to transfer $3,906,808 of Street Reconstruction Bonds from the 2020 Saint Paul Streets Program to the Ayd Mill Road Project; and

 

WHEREAS, there is a need to add $1,300,000 of Sewer funding to the Ayd Mill Road Project; and

 

WHEREAS, there is a need to remove $3,300,000 of 2019 Street Reconstruction Bonds from the Ayd Mill Road Project; and

 

WHEREAS, the Mayor, pursuant to Section 10.07.1 of the Charter of the City of Saint Paul, does certify that there is available for appropriation funds of $3,530,000; and

 

WHEREAS, the Mayor, pursuant to Section 10.07.4 of the Charter of the City of Saint Paul, does certify that there is available for transfer of appropriation of funds of $3,906,808; and

 

WHEREAS, the Mayor, pursuant to Section 10.9 of the Charter of the City of Saint Paul, does certify that there is a lapse of appropriation funds of $3,300,000.

 

NOW, THEREFORE BE IT RESOLVED, that the Council of the City of Saint Paul does hereby order that the above-described improvement be made, and the proper City officers are hereby directed and authorized to proceed with the improvement; and

 

BE IT, FINALLY RESOLVED, by the Council of the City of Saint Paul, upon recommendation of the Mayor and advice of the Long Range Capital Improvement Budget Committee, that $3,530,000 is available for appropriation, $3,906,808 is available for transfer of appropriation and there is a lapse of appropriation of $3,300,000 in the Capital Improvement Budgets, as heretofore adopted and amended by this Council, be hereby further amended in the Improvements Budgets in the following particulars:

 

Financial Analysis

See Attachment.

 

 CIB Recommendation

The St. Paul Long-Range Capital Improvement Budget Committee received this request on April 13, 2020, and recommends approval.

 

Date NameDistrictOpinionCommentAction
No records to display.