File #: RES PH 11-967    Version:
Type: Resolution-Public Hearing Status: Passed
In control: City Council
Final action: 7/6/2011
Title: Approving the application of the Metropolitan Council for a sound level variance in order to allow Central Corridor Light Rail construction between 10:00 PM and 7:00 AM from July 7, 2011 to August 31, 2011 along Cedar Street between 4th Street East and 7th Street East.
Sponsors: Dave Thune
Attachments: 1. SLV MetCouncilLtRailCedar4th-7th Application.pdf, 2. SLV MetCouncilLtRailCedar4th-7th District 17 Recommendation.pdf, 3. SLV MetCouncilLtRailCedar4th-7th ENS Notice.pdf, 4. Applicant MetCouncilLtRailCedar4th-7th SLV Notification Letter.pdf, 5. District Council 17 MetCouncilLtRailCedar4th-7th Notification Letter.pdf, 6. Property MetCouncilLtRailCedar4th-7th Notification Map.pdf, 7. Property Owners MetCouncilLtRailCedar4th_7th Notification List.pdf, 8. Property Owners MetCouncilLtRailCedar4th_7th Notification Letter Example.pdf

Title

Approving the application of the Metropolitan Council for a sound level variance in order to allow Central Corridor Light Rail construction between 10:00 PM and 7:00 AM from July 7, 2011 to August 31, 2011 along Cedar Street between 4th Street East and 7th Street East.

 

Body

WHEREAS, Chapter 293 of the Saint Paul Legislative Code was enacted to regulate the subject of noise in the City of Saint Paul; and

 

WHEREAS, §293.09 provides for the granting of variances from the sound level limitations contained in §293.07, upon a finding by the City Council that full compliance with Chapter 293 would constitute an unreasonable hardship on the applicant, other persons or on the community; and

 

WHEREAS, Kevin Ryan, Manager of Transitways Construction, Metropolitan Council, who has been designated as the responsible person on the application, has applied for a variance to allow Central Corridor Light Rail construction along Cedar Street  between 4th Street East and 7th Street East; and

 

WHEREAS, in order to minimize disruption to businesses, the public and adjoining property owners, the applicant is seeking a variance for the hours of 10:00 PM to 7:00 AM for up to ten (10) occurrences; and

 

WHEREAS, if applicant is not granted a variance it will not be able to complete construction within a timeline that would minimize disruption to businesses, the public and adjoining property owners; and

 

WHEREAS, the Department of Safety and Inspections has reviewed the application and has made recommendations regarding conditions for the variance; now, therefore, be it

 

RESOLVED, that the Council of the City of Saint Paul hereby grants a variance to the Metropolitan Council, subject to the following conditions:

 

1)      The variance shall be for up to ten (10) extended work periods of 10:00 PM to 7:00 AM from July 7, 2011 to August 31, 2011.

 

2)      The Council of the City of Saint Paul hereby grants the Department of Safety and Inspections the authority to approve extended work hours.

 

3)      The Department of Safety and Inspections may approve up to five (5) additional extended work periods to the Metropolitan Council during the time period set by this sound level variance.  If the Metropolitan Council finds that additional extended work periods are needed, the Metropolitan Council may request that City Council grant additional time periods without the need for a public hearing.

 

4)      When the 10:00 PM to 7:00 AM work hours are needed, the Metropolitan Council shall submit an extended work hour request to the Department of Safety and Inspections (DSI).

 

5)      The process for requesting work hours between 10:00 PM and 7:00 AM shall be as follows:

 

A.      Metropolitan Council shall submit a request in writing to the Department of Safety and Inspections a minimum of two (2) work days before the property owner notification date in E.

 

B.      The request shall include, but not be limited to, the specific date, time period, location, operation description and listing of expected noise sources such as generators, air compressors, jackhammers, excavators, skid loaders, etc. that will be used.

 

C.      The extended work hour request shall also include the name and phone number of a specific contact person for the work being done.

 

D.      Within two (2) working days of receiving the request, the Department of Safety and Inspections, in consultation with Department of Public Works, shall review and approve or deny the specific request and forward the determination to the Metropolitan Council.

 

E.      If the request is approved, the Metropolitan Council shall notify in writing, all property owners within 200' of proposed work location.  Notification shall be a minimum of 72 hours prior to the start of the work. A copy of the property owner notification shall also be sent to the Department of Safety and Inspections.

 

F.      The Metropolitan Council property owner work notification shall include, but not be limited to, the specific date, time period, location, operation description and listing of expected noise sources such as generators, air compressors, jackhammers, excavators, skid loaders, etc. that will be part of extended work hours.

 

G.      If there is an emergency, where immediate work is necessary to restore property to a safe condition or to protect persons or property from an imminent exposure to danger, the Metropolitan Council or its designee, shall notify the Department of Safety and Inspections and make a good faith effort to inform property owners within 200 feet of the work location.  Notification of the Department of Safety and Inspections and property owners may be done after the work has begun or if possible, before the work has started.

 

6)      The Contractors and Utility Companies working on the project shall use best practicable methods for controlling noise. Construction activities shall be scheduled to minimize noise as much as possible in the early morning hours. Requests for construction activities between 10:00 PM and 7:00 AM will only be done if there are no other reasonable alternatives.

 

FURTHER RESOLVED, that any violations of the conditions set above may result in denial of future requests for the grant of a sound level variance, in addition to any criminal citation which might issue.

 

Required Background Information

The Metropolitan Council, represented by Kevin Ryan, Manager of Transitways Construction, has requested an exemption from the sound level limitations in Chapter 293.07 in order to allow Central Corridor Light Rail construction for up to ten (10) occurrences between 10:00 PM and 7:00 AM, from July 7, 2011 to August 31, 2011 along Cedar Street, between 4th Street East and 7th Street East in Saint Paul.  A process is provided for requesting additional occurrences if needed.  Chapter 293.09 provides for the granting of variances from the sound level limitations contained in Chapter 293.07.

 

Was proper notice given?  YES - See Attachments