title
Approving a Five-Year Street Reconstruction Plan for the Fiscal Years 2025 through 2029 and granting preliminary approval to the issuance of certain General Obligation Street Reconstruction Bonds by the City.
body
WHEREAS, the City of Saint Paul, Minnesota (the “City”) annually adopts its Capital Improvement Budget and Program (the “CIB”) which plans for certain street improvement and street reconstruction projects in the City for a five year period; and
WHEREAS, Minnesota Statutes, Section 475.58, Subd. 3b, as amended (the “Street Reconstruction Act”) authorizes the City to issue general obligation street reconstruction bonds for the funding of street reconstruction and bituminous overlays if certain conditions are met, including the adopting of a five year street reconstruction plan after a public hearing on such street reconstruction plan; and
WHEREAS, the City has created a Five-Year Street Reconstruction Plan for the Fiscal Years 2025 through 2029 (the “2025 SRP”) to identify the anticipated street reconstruction projects in the City for the next five years and provide for necessary street reconstruction expenditures and to economically schedule those anticipated expenditures over the five-year period; and
WHEREAS, the City wishes to issue up to $28,800,000 of General Obligation Street Reconstruction Bonds (the “Street Reconstruction Bonds”) pursuant to the provisions of the Street Reconstruction Act and Minnesota Statues, Chapter 475, as amended, for the purpose of (i) funding certain mill and overlay and street reconstruction projects in the City identified in the 2025 SRP, and (ii) paying costs of issuance of the Street Reconstruction Bonds; and
WHEREAS, Street Reconstruction Bonds are anticipated to include (a) approximately $5,300,000 of general obligation bonding authority that was approved in late 2021 and 2022 for the 2022 and 2023 street reconstruction plans, respectively for mill and overlay and the Saint Paul Streets projects in 2022 that were approved after public hearings and have not been previously issued by the City, (b) approximately $8,000,000 of general obligation bonding authority that was approved in 2023 for street reconstruction projects in the 2024 street reconstruction plan that was approved after a public hearing on December 6, 2023 and have not been previously issued by the City, and (c) $15,500,000 of new authorization of general obligation bonds for street reconstruction projects described in the 2025 SRP.
WHEREAS, the Street Reconstruction Act requires that the City Council of this City hold a public hearing with respect to the 2025 SRP and the issuance of the Street Reconstruction Bonds in order to finance the projects set forth in the 2025 SRP; and
WHEREAS, City staff has prepared the 2025 SRP with respect to the proposed street reconstruction projects and in such 2025 SRP the street reconstruction projects have been presented to and the factors set forth therein have been considered by this City Council; and
WHEREAS, on the date hereof, prior to consideration of this resolution, this City Council held a public hearing with respect to the 2025 SRP and the issuance of the Street Reconstruction Bonds; after notice of such public hearing was published as required in the Street Reconstruction Act, and the public was given an opportunity to comment on the proposed 2025 SRP and the proposed issuance of the Street Reconstruction Bonds; and
WHEREAS, the notice of public hearing for the 2025 SRP and the issuance of the Street Reconstruction Bonds was published in the Pioneer Press, the official newspaper of the City, on November 27, 2024, which date was not more than 28 days and not less than 10 days prior to the date of the public hearing; and
WHEREAS, the issuance of the Street Reconstruction Bonds is subject to the requirement that the City does not receive a petition within thirty (30) days signed by five percent (5%) of the voters from the last municipal general election requesting that the City hold an election prior to the issuance of the Street Reconstruction Bonds.
NOW, THEREFORE BE IT RESOLVED by the Council of the City of Saint Paul, Minnesota, that
1) The Director, Office of Financial Services, City Treasurer, and other appropriate City officials and staff are hereby authorized and directed to proceed with the actions necessary to facilitate the financing of the mill and overlay and street reconstruction projects in accordance with the 2025 SRP and the issuance of the Street Reconstruction Bonds. The Public Works Director and other appropriate City officials and staff are authorized and directed to proceed with the actions necessary to effectuate the mill and overlay and street reconstruction projects set forth in the 2025 SRP.
2) The actions of the City staff to publish the notice of public hearing with respect to the 2025 SRP and the Street Reconstruction Bonds are hereby approved and ratified.
3) The 2025 SRP is hereby approved in the form attached hereto as Exhibit A.
4) Baker Tilly Municipal Advisors, LLC, as municipal advisors to the City, and Ballard Spahr LLP are hereby authorized to work with City staff to prepare the documents, instruments and certificates as may be necessary for further approval of this by City Council for the issuance and sale of the Street Reconstruction Bonds.