Preliminary Order setting the date of Public Hearing for January 27, 2027, to consider approval of the Arlington Avenue Reconstruction Phase I - Common Cent Project (Project No. 19281, Asmt. No. 275201).
Body
In the Matter of approving the pavement conditions on the following street segment:
Arlington Avenue - Jackson Street to Edgerton Street
Improvements to be made as part of the project include reconstructing the roadway as a 2-lane roadway with reduced parking and repurpose the excess space for an off-street shared use path on the south side. Sidewalks will be added where none currently exists on the north side. The project will upgrade existing pedestrian ramps to current Americans with Disabilities Act (ADA) current standards. Lighting and utility improvements will be made with the project and Sanitary sewer services and their connection to the sewer main can be replaced at the request of the property owners.
The Council of the City of Saint Paul, having received the report of the Mayor upon the above improvement and having considered said report, hereby resolves:
1. That the said report and the same is hereby approved with no alternatives, and that the estimated cost thereof is $20,420,000, financed by Common Cent Sales Tax, Federal Funding, Saint Paul Regional Water Services, Sewer Repairs, and Assessments.
2. That a public hearing be had on said improvement on the 27th day of January, 2027, at 3:30 p.m., in the Council Chambers of the City Hall and Court House Building in the City of Saint Paul.