Layover to LH April 23, 2024 at 10 am for status update (permits finaled/issuance of
CC certificate).
Shannon Powell, Freedom Mortgage, appeared via phone
Staff update by Supervisor Matt Dornfeld: February 28 the City Council granted to
March 25, 2024 to abate the nuisance. Legislative Hearing was scheduled for April 9,
2024 to find out current progress, which is at 80%.
Moermond: has it been maintained?
Dornfeld: yes, it is has. No complaints from the neighbors lately. There is some
sensitivity in the neighborhood.
Moermond: you were having some difficulty with the contractor on the ground giving you
different information than what the City had. He was saying done, City was saying no
finaled permits. Have you talked to them?
Powell: I spoke with my contractor yesterday and they flew their senior person out to
St. Paul to walk thorugh with Clint so everyone was on the same page. The problem
was the photos didn’t show some of the things Mr. Zane wanted to see done. As of
yesterday, the exterior we have repair or replace something near the entry door and the
exterior wood window trim with mold, which will be replaced this week. The interior
should be completed today, but I haven’t followed up with them. Drywall seam and mud
taping. The Kitchen they’re installing the remaining cabinets and getting a permit for
the gas to the stove. I talk to them at 2 daily. The bathroom they have scheduled for
this week with the tape, mud and sanding. That will take until next week. The trip
hazard in the room off the kitchen the wood frame is being removed and will be done
this week. 3 bedrooms need some drywall repair, which should be done this week.
Basement hallway has a transition strip and some drywall and adding baseboards, as
well as the living room. That should be done by early next week. The 4th bedroom has
some more sheetrock. Final weatherstripping and then cleaned. My contractor said the
photos were not as clear so when Lou did the walkthrough he said there were these
items. They’ll make it right and we should have everything wrapped up by end of next
week, aside from the permit piece for the gas line. I think the confusion was he
thought we’d contract with HUD and they would have accepted it this way, but we have
made it clear that St. Paul Minnesota does not.
Moermond: it sounds like we should be wrapped up by the Council Public Hearing.
We’ll talk again April 23, and if you aren’t done you’ll be within a breath of that. I feel
good about this. I appreciate you taking care of business on this.
Referred to the City Council due back on 4/24/2024
4
First Making finding on the appealed substantial abatement ordered for
1356 REANEY AVENUE in Council File RLH RR 23-23. (Refer back to
April 23, 2024 Legislative Hearing)
Johnson
Sponsors:
Refer back to LH April 23, 2024 at 10 am for further discussion.
Jodisha Darrough, potential purchaser, appeared via phone
Joe Steinmaus appeared via phone
Kevin Vu, potential purchaser, appeared via phone