Moermond: you submitted a work plan dated May 30, 2023 would have taken into
account a lot of what you are talking about and it basically said the project could be
done in four months. The delays are delays that doubled the time you estimated. I
would have expected that kind of delay could have expected that delay could have
been done in the granted time.
Grimm: me too. I totally agree. At the same time, here we are and we’re $130,000 deep
into this and almost done. I’ll stand by my opinion that having installed the new furnace
and new duct work and the plumbing rough in done, the inspector for the electrical
rough in should be called by end of week. Those pieces, once the mechanicals are
roughed in and completed it should go much more smoothly. We’ve corrected the
major problems bogging us down.
Moermond: and this plan from Monday asks for another 90 days. Because we do have
a progress rating less than 50%, you’re in a position of forfeiting the $5,000
Performance Deposit. Instead of doing that I’d like to ask them to continue that
Performance Deposit but have you put another $5,000 down in Performance Deposit
and ask them to give you another 180 days to finish this. In for more money and have
a lot more time. If you finish, you’ll get all that money back again.
Grimm: that works for me.
Moermond: we’ll send this to Council March 6. Have the Performance Deposit posted
by February 27.
Grimm: there was a time right after the original time ended, January 31, where we
couldn’t pull permits and because of the deadline passing Department of Safety &
Inspections wouldn’t allow it. I think they are now pulled, I just wanted to request if the
ground could be cleared, as it were, for us to continue work between now and March 6.
Moermond: that won’t be a problem. Mr. Yannarelly can put a note in the system noting
you can pull permits after you post the additional $5,000. He did mention a work order
to clean the backyard, I hope that’s done already.
Grimm: I’ll make sure it is done.
Referred to the City Council due back on 3/6/2024
2
RLH RR 23-70
Second Making finding on the appealed substantial abatement ordered
for 342 THOMAS AVENUE in Council File RLH RR 23-46.
Balenger
Sponsors:
If CC certificate isn't issued by March 13, 2024 forfeit $2,500 of the PD and continue
PH to March 20. If still no CC certificate issued, forfeit remaining $2,500 of PD.
Manuel Crespo, owner, appeared
Moermond: this is the second time we’ve had a conversation about finishing the job.
Staff update by Supervisor Joe Yannarelly: since the last hearing there’s been no
problems and the Building Inspector says 90% complete.
Moermond: last time was 80%.
Yannarelly: on January 16th. Seems close.