comprises a nuisance as defined by the legislative code. Taxation has placed an
estimated market value of $3,893,800 on the land and $390,500 on the building. Real
estate taxes are current. The vacant building registration fees were paid by
assessment on April 3, 2023. As of August 21, 2023, a Team Inspection has not been
done. As of August 21, 2023, the $5,000 performance deposit has not been posted.
There have been sixty-one Summary Abatement notes since 2008. There have been
thirteen work orders issued for boarding/securing.
Also, for the record, an Order to Abate an open and free flowing well was issued to the
property owner/responsible parties on January 31, 2012 with a compliance date of
March 1, 20212. The owner requested an extension to comply with the orders on
February 23, 2012 which was granted. When compliance was not achieved, a letter
was sent to the owner by the Minnesota Department of Health on April 3, 2012 advising
that the unsealed well was in violation of state law. On April 9, 2012, the inspector
noted that the well was no longer leaking and the order to abate was now in
compliance. Code Enforcement Officers estimate the cost to repair this structure
exceeds $500,000. The estimated cost to demolish exceeds $100,000.
Moermond: 61 notices, but only 13 work orders.
Yannarelly: they are fairly responsive. We have also issued orders for cleaning up. The
only work orders have been to board. We don’t send notices on those, if it is open,
we’re boarding it.
Moermond: the work orders are late 2021 through the present, they took care of things
prior to that much better. No graffiti orders in spite of it being plastered with graffiti.
And the number of work orders because--
Yannarelly: it has been discovered by the unsheltered.
Moermond: no question this has to be ordered removed within 15 days with no option to
repair.
Referred to the City Council due back on 9/27/2023
7
RLH RR 22-48
Ordering the rehabilitation or razing and removal of the structures at 523
BEAUMONT STREET within fifteen (15) days after the September 21,
2022, City Council Public Hearing.
Noecker
Sponsors:
Grant 180 days pending submission of updated work plan/bid and updated letter of
financing.
Ed Dropps, Greater Midwest Realty o/b/o GITSIT Solutions, appeared via phone
Araiza Hargrove, GITSIT Solutions, appeared via phone
Joy Zimmerman, REO o/b/o GITSIT, appeared via phone 714-640-2657
Moermond: this was an opportunity to touch base on the foreclosure. We have some
updated information from you, let me find out how the foreclosure process has gone.
Hargrove: the redemption period has expired, so we are now the owners and can move
forward with starting the repairs. The last we spoke regarding the rehab was our
contractor had an earliest start time of September 5, so we’re looking to move forward.
Moermond: I see a new letter dated August 21 indicating 60,000 is set aside for the
project.