Marks: no:
Moermond: often at a year in I look at posting more Performance Deposit. You sound
like you’re 4 months out from being complete. Permits are in a good place. I’m not
going to ask for additional Performance Deposit. I’d love to see this done by
September 5, so if I review the file Monday the 8th everything is done. Is that doable?
Marks: I absolutely hope so.
Moermond: if not, we’ll start forfeiting money. That’s four months from May 7th when
Council votes.
Marks: part of my agreement was Dennis was responsible for outstanding taxes.
There’s a Vacant Building registration fee.
Moermond: that’s a prospective fee October 2024 to October 2025. The only way I’d
look at prorating it is if its less than 6 months into the billable year. I wouldn’t waive
Vacant Building fees if it’s a Category 3, and this is past the 6-month mark already.
Those are the normal standards, there could be exceptional circumstances of course.
By the time you’re done you’re 9 months into the 12-month year, but it costs you
nothing to appeal.
Referred to the City Council due back on 5/7/2025
2
RLH RR 25-13
Second Making finding on the appealed substantial abatement ordered
for 1213 WOODBRIDGE STREET in Council File RLH RR 24-41.
Kim
Sponsors:
Grant to September 5, 2025 to complete rehab and continue $10,000 PD. If CC cert is
not issued by September 5, forfeit $1,000 of PD each week beginning September 17th
CPH until project is complete.
Michael Sauer, attorney, appeared
Staff update by Supervisor James Hoffman: per client were at 50% progress with a
new General Contractor. ETA of completion July 11. Mechanical, gas, plumbing and
building permits all active from a week ago.
Moermond: we had 35% in September 2024 and in April 2025 we’re at 50%. When did
you switch contractors?
Sauer: this is the third contractor. The first two just weren’t the right fit for a job like
this. They said they could manage it, made an attempt, and were above their
capabilities. My understanding is Solid Rock has done jobs like these before and so
they hired based on communication with City inspectors. I believe they were hired in
the last month. They gave me a new timeline to the extent that they’re accurate they’re
saying July 15th. This has all the trades with expected dates and final date of July 15.
I’ve seen some photos; the trades were started but contractors didn’t follow through.
They’d just stop responding, I’m not sure why it happened. It wasn’t money. I guess it
just happens when you hire people with the resources and staffing to get it done. Solid
Rock is experienced as I understand it. I have a lot more faith on the July completion
date than in the past.
Moermond: you have $10,000 in Performance Deposit posted.
Hoffman: there were lots of inspections, like insulation was approved.