Saint Paul logo
File #: RES PH 21-78    Version: 1
Type: Resolution-Public Hearing Status: Passed
In control: City Council
Final action: 4/21/2021
Title: Amending the financing and spending plans in the Department of Public Works Capital and Operating Budgets for the 2021 Sidewalk Reconstruction Program, the 2021 Jefferson/St Paul Avenue Pedestrian Improvement Project and the 2021 Griggs/Scheffer Phase II Project.
Sponsors: Amy Brendmoen
Code sections: Sec. 10.07.1. - Supplemental appropriations., Sec. 10.07.4. - Transfer of appropriations.
Attachments: 1. RES PH 21-78 Sidewalks and Ped Improvements
Title
Amending the financing and spending plans in the Department of Public Works Capital and Operating Budgets for the 2021 Sidewalk Reconstruction Program, the 2021 Jefferson/St Paul Avenue Pedestrian Improvement Project and the 2021 Griggs/Scheffer Phase II Project.

Body
WHEREAS, the Department of Public Works plans to reconstruct sidewalks as part of the Downtown Street and Sidewalk Improvements Program; and

WHEREAS, sidewalk reconstruction in the downtown area is 100% assessed to abutting property owners; and

WHEREAS, the Department of Public Works recommends adding $582,156 of assessment financing to the 2021 Sidewalk Reconstruction Program; and

WHEREAS, the 2021 budget includes $1,300,000 for pedestrian improvements to be completed in coordination with the Mill and Overlay Program; and

WHEREAS, the pedestrian improvements will be completed with the 2021 Jefferson/St. Paul Ave Pedestrian Improvement Project and the 2021 Griggs/Scheffer Phase II Project; and

WHEREAS, there is a need to transfer $1,150,000 of the pedestrian improvement funding to the 2021 Jefferson/St. Paul Avenue Pedestrian Improvement Project and $150,000 to the 2021 Griggs/Scheffer Phase II Project; and

WHEREAS, the Seal/Territorial Pedestrian Improvement Project will be completed with the 2021 Sidewalk Reconstruction Program; and

WHEREAS, there is a need to transfer $141,190 of CIB funding from the 2021 Seal/Territorial Pedestrian Improvement Project to the 2021 Sidewalk Reconstruction Program; and

WHEREAS, the Mayor, pursuant to Section 10.07.1 of the Charter of the City of Saint Paul, does certify that there is available for appropriation funds of $582,156; and

WHEREAS, the Mayor, pursuant to Section 10.07.4 of the Charter of the City of Saint Paul, does certify that there is available for transfer of appropriation funds of $1,441,190 now, therefore be it

RESOLVED by the Council of the City of Saint Paul, upon recommendation of the Mayor and advice of the Long Ran...

Click here for full text
Date NameDistrictOpinionCommentAction
No records to display.