title
Authorizing not using a Project Labor Agreement (PLA) for the following projects: Sewer Cleaning and Televising Projects (Como-Cleveland and Snelling-Larpenteur), Phalen Storm Tunnel Rehabilitation Project (Phase 3), 2018 Citywide Sewer Repair Project, Cherokee Heights Upper Ravine Stabilization Project, and the 2018 Citywide Sewer Lining Project.
body
WHEREAS, the Saint Paul City Council adopted a policy on the use of Project Labor Agreements ("PLA") pursuant
to Council File #09-584 for projects involving $250,000 or more of city money; and
WHEREAS, the Public Works Sewer Utility is undertaking sewer related cleaning, inspection, and repair projects, with project
total budgets over $250,000:
Sewer Cleaning and Televising Projects (2- projects, Como-Cleveland and Snelling-Larpenteur)
Project Description: Clean and televise sanitary sewers and manholes, and televise storm sewers and manholes
Estimated Cost: $500,000 for each project
Estimated Start Date: Spring 2018
Estimated Project Timeline: 6 months
Phalen Storm Tunnel Rehabilitation Project (Phase 3)
Project Description: Chemical grout tunnel liner cracks, concrete repair, corrosion protection of exposed steel reinforcement, repair tunnel inverts
Estimated Cost: $2,500,000
Estimated Start Date: Fall 2018
Estimated Project Timeline: 6 months
2018 Citywide Sewer Repair Project
Project Description: Repair broken sewer piping and/or manholes via excavation in public streets
Estimated Cost: $500,000
Estimated Start Date: Fall 2018 or Spring 2019
Estimated Project Timeline: 2 months
Cherokee Heights Upper Ravine Stabilization Project,
Project Description: Regrade and stabilize ravine located downstream of city culvert, install riprap, surface restoration
Estimated Cost: $700,000
Estimated Start Date: Fall 2018
Estimated Project Timeline: 9 months
2018 Citywide Sewer Lining Project
Project Description: Clean and televise sewers, install cured-in-place liner inside existing sewer, re-tel...