Saint Paul logo
File #: RES PH 14-93    Version:
Type: Resolution-Public Hearing Status: Passed
In control: City Council
Final action: 7/9/2014
Title: Approving the Saint Paul long-term streetcar network, and authorizing a detailed study of East to West Seventh from Arcade to Randolph, for the potential of a starter streetcar line.
Sponsors: Russ Stark
Attachments: 1. Planning Commission Resolution, 2. Memo from Transportation Committee to Planning Commission, 3. Final Streetcar Feasibility Report, 4. Streetcar Study outreach efforts, 5. Streetcar public comment, 6. Wuollet Bakery letter re Grand Ave Streetcars, 7. Harris email, 8. Mills Streetcar Study opposition, 9. Streetcar Study Opposition - Rubinstein, 10. Email in Opposition of Streetcar - Newburgh, 11. Olson email, 12. ESABA Streetcar support letter, 13. SmartTrips, 14. Hambridge email re Streetcar study, 15. Opposition to streetcar study, 16. May email in support, 17. Phone messages against streetcar, 18. Mason email, 19. Gustafson comment, 20. Van opposition, 21. Russ email, 22. Opposition to streetcar study, 23. Bayuk letter of support, 24. Streetcar PH handout
Title
Approving the Saint Paul long-term streetcar network, and authorizing a detailed study of East to West Seventh from Arcade to Randolph, for the potential of a starter streetcar line.

Body
WHEREAS, the Saint Paul Comprehensive Plan includes strategy 2.10 Study the feasibility and possible location of new streetcar lines, to help provide balance and choice to the system; and

WHEREAS, the Saint Paul Department of Planning and Economic Development engaged a team of consultants from Nelson\Nygaard, HDR and Richardson Richter and Associates, with funding from the Central Corridor Funders Collaborative, the Saint Paul Foundation, the McKnight Foundation, the Ramsey County Regional Rail Authority and the City of Saint Paul, in a technical Streetcar Feasibility Study, and identified a network of feasible routes as well as a priority corridor; and

WHEREAS, the Planning Commission, on December 6, 2013, released the draft study and recommendations for public review and set a public hearing for January 24, 2014; and

WHEREAS, notice of the hearing was published and mailed to the early notification system list and other interested parties; and

WHEREAS, public testimony was accepted via Open Saint Paul and at two Open Houses held on January 15th and 16th, 2014; and,

WHEREAS, a public hearing on the Streetcar Feasibility Study was conducted by the Planning Commission on January 24, 2014, at which all persons present were allowed to testify; and

WHEREAS, the Planning Commission referred the draft study and conclusions to the Transportation Committee for consideration, review of the public testimony, and recommendations; and

WHEREAS, on February 10, 2014, the Transportation Committee forwarded its recommendations to the Planning Commission; and

WHEREAS, the Planning Commission considered the public testimony and the recommendations of the Transportation Committee;

WHEREAS, on February 21, 2014, the Planning Commission recommended approval of the long-term...